Field name in the satellite table |
|
PSP_ACT_CUMULATE
This constant defines to which level a project should be relevant for Allevo, and if necessary only the WBS elements up to the defined level are written in the satellites. For the determination of the relevant cost elements, the subordinate WBS elements are also considered.
To have the correct display in Allevo-MultiObject, the constant of the same name should also be set. Then, the cumulative costs of all of the subordinate levels appear for the WBS of the selected level.
The level must be entered in the column Value from (differing from the entry of the constant of the same name in Allevo).
|
Note: |
Only available for object type PR. |